‘Auto Dispute Write-off Program – RFDM2000’
A dispute case got approved on 07/31 and got closed on same day at 11:00 PM SAP system time as per job schedule.
Issue:
The clearing document is showing both document date and posting date as 08/01/2023 whereas the dispute got closed on the night of 0731/2023.
Header Data:
Document Type: AB (Accounting Document) - Clearing Document
Entry Date: 07/31/2023
Time of Entry: 23:00:18
Document Date: 08/01/2023
Posting Date: 08/01/2023
Can you please advise on why/how system is determining the document date and posting date as future date? and how do we restrict it?