Exception Message: Want Purchase Orders After Lead Time/PDT to Be Cancelled and Not Postponed

65 Views Last edit Aug 03, 2023 at 07:36 PM 3 rev

Hi,

My understanding is that if the system no longer has a requirement on X date, it will seek to postpone that delivery / purchase order to the next available requirement. If a requirement can not be found, it will generate a cancellation message.

What I would like to happen: If the system finds a requirement, but it is after the planned delivery time, I want it to generate a cancellation exception message, not a postpone message. The reason for this is that I have requirements loaded out several years for accounting purposes. That said, those requirements can vary month to month and I want to wait until as long as possible before committing to a purchase order. I would rather ask the supplier for a cancellation upfront and re-plan at a later date. Is there a setting that can be adjusted for this logic?

Example:

Current Month is July

Raw Material A has a 3 month lead time

I have a total requirement of 90 units for raw material A for the remainder of the year and 100 units for next year

I have purchase orders placed for 100 units this year and 0 placed for next year

Current Logic

100-90 = 10 Excess

Exception Message to postpone process with re-scheduling date next year

Desired Logic

  • 100-90 = 10 Excess
  • Lead time is 3 months, therefore exception message to cancel process and re-place order later in the year.
  • IF delivery qty is greater than requirements AND reschedule date is greater than the planned delivery time THEN Cancel Process