Alternative-Based Confirmation (ABC) in ATP does not consider the main plant when answered.

341 Views Last edit Aug 09, 2023 at 09:50 PM 5 rev

I am performing condition-based availability check (ABC) configuration. When carrying out testing the substitute plant is always determined even if the original center is serviced.

Example:

For material 1196, 30 PEC´s were requested and I have the following availability below:

BR01 - 50 PEC´s (Main Center)

BR02 - 55 PEC´s (Substitute Center 2)

BR03 - 80 PEC´s (Substitute Center 3)

In the RACR, as shown in the image below, the replacement is carried out even if it is available at the main center.

image.png

image.png

How to keep the availability check when the original plant is not attended?