Hi all,

I want to know why the actual costs in global currency is different with actual costs in project currency.

For project R.100010, the cost number 945 is from sales order (done billing)

But I don't know what the number 998.4 comes from. which means there is 998.4-945=53.4 difference...

The two currency is CNY. Do you have any suggestion and opinion to let me check?

11111.png

Many thanks,

Chen