Hi,
I have just completed my first S4/HANA public cloud implementation project on 2SL and am about to start the next on 3SL. I am looking for the recommended approach as far as the production deployment is concerned in line with the Activate Methodology:
Do I deploy the configuration to production at the end of each Sprint or cumulatively at the end of all Sprints?
I seem to recall SAP did change the guidance on this and it used to be after each Sprint which in fact I did at my last project. Not sure if this is different in a 3SL environment. I personally did like the approach of moving everything at the end of each Sprint which made the subsequent cutover much easier and allowed to focus purely on the data migration...
Any thoughts?
Thanks,
Manuel