Dear All,

I have released project and WBS completely.Now adding one network to released WBS but it is coming in REL status automatically. Due to business requirement new network must be in CRTD status. Project and WBS are already released in live server so this is the only option left to have network in CRTD status by any means. Please tell me how to achieve this ?

As per SAP standard once WBS released and new network is added then network gets automatically released. How to prevent this problem.

Please help on this asap.

Many Thanks

Ankit Upadhyay

Accepted Solutions (1)

Accepted Solutions (1)

kenmelching
Active Contributor
0 Kudos

You will need to release from the bottom up. Do not Release the Project Definition, that will release everything below it. Once an object is released everything below it is released as well and new objects will be released automatically upon creation. It is best to wait and release from the bottom up.

You could assign the NW to an unreleased WBS, then reassign it when you are ready to release it.

If you have released the Project Definition you are kind of stuck at this point.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

you should check your network customizing, because there is a setting to create a network with REL status by default.

Per standard behaviour, network is created with CRTD status, even if WBS is in REL status

Former Member
0 Kudos

Hi Ken

Thank you very much