on 03-28-2023 10:19 AM
Hii,
In Public Cloud version 2302, EPPM
I have created one investment project and maintained budget availability control key
when we create a Purchase requisition or purchase order with account assignment category Q (project stock), my budget Availability control is not triggered even if my budget exceeds.
After the create PR/PO my commitment cost was also not shown in the Project budget report tiles.
kindly suggest solution
Thanks & Regards,
Hello,
SAP gave the reply to this question
This feature is currently not available in the Public cloud 2302 product- it is already part of product roadmap.
Posting where goods are procured for project stock (Q), this result in a balance sheet posting to update inventory rather than a P&L posting and so these costs are ignored during the budget availability control check. Currently, balance sheet postings are not supported by the commitments solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shubham,
Commitment is a CO document, to trigger CO document you need a cost element, so your material GL account master record needs a check box to get that statistical posting. I am assuming here that Cloud should not differ from the on-Prem for such basic things.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.