Hi All,
Some days back we got a situation where one alternative resource is being used in PV but in APO while checking PDS we saw 3 alternative resources are there. We did re transfer of PV in APO and issue got solved. But user wants to know the root cause why it happened. We saw there are no recent changes made (like addition of extra two alternative resource in ECC). Can anyone help me on this? Currently we are having the same data in quality.
PV is using only one Alternative Resource

PDS Alternative Resource