Hello all,
I have a issue on the workcenters in cm21 where it's causing overlapping of FG planned orders,and i do not want that to happen.
The issue is that after i dispatch all planned orders in the sequence that is needed,the folowing day,the remaining qty from previous planned orders that are in backlog are moved forward automaticaly by the system,causing this overlapping.
Settings now
cr02 - box "Can be used by several operations" unchecked
ca22 - Overlapping- set to "no overlapping"
Do you know what setting is causing this ?overlapping-cm21.png
Thank you in advance for your support