Hello Experts,
Project System: Workaround for Budget availability control is not working and the project budget report is also not showing correct data due to the same for Account assignment category Q in S/4 HANA public cloud in the Project system.
As SAP has not supported Budget availability control to check the budget for the PR/PO of account assignment category "Q" project stock on SAP public cloud as we have it in GUI, and which Project standard budget report is made by maintaining G/L in FSV(Financial Statement Version) in which it only supports P&L G/L but not Inventory G/L.(Balancesheet G/L)
Regards