I am a newbie in this field. Currently during my study, I had a questions about MM module as follows.
Hope you can help me. Thank you ��
【SAP (MM)】This is a question about system operation in SAP. Based on the business rule that a Purchasing Requisition must be made 60 days in advance for items such as new parts for which the delivery date cannot be predicted, standard delivery lead time (LT) is set to 60 days for new part numbers. How should I operate SAP as a standard usage?
Issue: Currently, I make Purchasing Requisition with an LT 60 days, and after the requirement explosion, the purchasing department negotiates the delivery date with the customer for the parts that have been set to LT 60 days, and rewrites the delivery date to the correct delivery date. But at the site level, it causes confusion as to which LT is correct , and it also induces delivery deadline.