Hello,
In R/3 is there any way to run missing parts but split for daily basis? Problem is that in MTS scenario, when running ATP check for upper production order, missing parts tells us that the below production order material only full available at the end of the total production. And this function is not reliable for orders that take long. As long as I know, GLEI does not help with that.
Thanks and Kind Regards