Second Level WBS Element -existing Project using BAPI_PROJECT_MAINTAIN

60 Views

Dear Experts,

I need to upload 2nd level WBS element to the existing project. according to my program logic, the new WBS is assigned as 1st level element and updated in the bottom line of the structure.

Needs to update WBS element FM21AP220001552007640015 to under the 2nd element of FM21AP22000155.

( Pls ref 2nd image ).

Pls advise me, if I am doing any incorrect table updates.

- WBS updated incorrect position with existing logic

image.png

- Required position to update

image.png

Below are the filled internal tables for BAPI_PROJECT_MAINTAIN.

image.png

- it_projmethod

image.png

- it_uwbs_element_upd

image.png

- it_uwbs_element

image.png

- it_wbs_hierarchie_table

image.png

Thanks

Pramod