Hello,

We are facing the following issue :

Customer transmits forecasts data that we integrate through DELINS message in schedule agreement and then firm data via another type of message (DELORD) same delivery date.

We expect the forecast quantities to be consumed by firm quantities in MD04 screen :

If I have 100 in schedule lines (schedule agreement), then I create a sales order of 100 in reference to SA. MD04 should display only sales order schedule line. The issue we face : we see both quantities, from schedule agreement and delivery order, so production planning is consequently wrong.

Customizing has been checked item category / scheduline line category/ copy control

No clue so far. May I ask for your support on this point ?

Thanks in advance and Best Regards