Skip to Content
0
Jan 24 at 04:56 PM

PM02 Control Key

69 Views

I created a work order and changed the control key to PM02 for external labour.

Once all information is populated I go to the cost tab and the financials are populated into the "internal labour" section.
Is this a default for PM02? How could I get the costs for the contractor into the external labour of the cost tab?