Jan 19, 2023 at 09:53 AM

SOURCE LIST & PURCHASE REQUISITIONS- SAP ERP MM

37 Views

Hello everyone,

Suppose I have a part that I've added to an outline agreement on line 100 with a target quantity of 50 pieces. These 50 pieces have been released through multiple call-offs, some of which have been delivered (let's say 20 pieces) and others, still yet to be delivered (30 pieces). Now, I have two questions:

1. Will closing the source list (for line 100 of the outline agreement) by checking the Blk indicator in ME03 have any negative impact on the undelivered quantities on the call-offs? My assumption is that it wouldn't and that I should be able to "block" the source list lines (as there is no open target quantity on the outline agreement line 100) without any negative consequences on the undelivered call-offs.

2. If I were to have Z quantities in purchase requisitions for this same part, will blocking the source list increase the quantity of purchase requisitions for said part to 80 pieces? Again, my assumption is that it shouldn't as the quantities that were already released will still be tied to the call-offs regardless of the delivery status.

I would like to ask the knowledgeable community here. I know it sounds like a high-school math problem. It wasn't intentional :)


Thanks!