Hi,
We are facing issue in Planned Activity Cost calculation such that:
In KP26 we have set a value of 1147 in Price (Fixed) column for UoM KwH for January of 2023 and all the rest of the months are kept 0 (screenshot attached of Overview/detail screen).
Our Routing is set such that for 1kg Production, the Electricity consumed will be 1KwH.
When we create Production Order for 1kg and calculate Cost, we expected to see the Planned Cost as 1147 for the Activity but it appears as 95.58 i.e. 1147 /12.
Our objective is to use the exact Price for that month, as value may differ for different periods.
Regards