Experts, I have a planned independent requirement for Jan 25th and for some reason i have a planned order to fulfill this requirement on Jan 30th..what i am looking for is when I run detailed scheduling heuristics/function I need the planned order to be rescheduled to Jan 24th ( i have capacity on that day )..my goal is to move the future planned order to as close as or as timely as possible to my requirement date but still before the requirement date..
When I try current date scheduling and backward, the planned order does not move.. when i do earliest date it moves to todays date ( too early)..
How can i achieve my requirement?