IDLE Budget - PR vs LPO

47 Views

Hello,

I have a quick question, when an PR is being generated using Internal Order, and the Same PR get converted to LPO, but with a special discount.

For Instance, Internal Order Budget is for 100K, PR used for 60K. when processing the LPO, there is a discount of 20K so, the net budget utilized is 40K for LPO.

The budget of 20K being as discount is IDLE(Unused) thus reducing the main budget by same amount,

At this time the budget available should be 60K. (i.e adding back of 20K discount back to main Internal order) but that doesn't work.

Is there any solution for the above issues.

looking for support thanks :)