Skip to Content
0
Jan 16, 2023 at 11:26 AM

PS MRP (MD51) using Easy Cost Planning (CJ9ECP) without network

130 Views

Hi All,

I am trying to use PS MRP (MD51) using Easy Cost Planning (CJ9ECP) without network. I am creating reservations through Easy Cost Planning (CJ9ECP). They are created for movement type 221 and without special stock. But I'm already changing (via user exit) to special stock Q.

However, I'm not getting any results from executing the Project MRP (MD51). Does anyone have any suggestions or indications of the prerequisites for using the MD51 without a network and with reservations coming from the ECP?

Thanks,

Andreia