Hi Experts,
Greetings !!
Our business is a Food processing industry. They have change over time which will be taken into account when they change Production from one product to other product.
Example:
Similar way they have a fixed Change over matrix.
Master Recipe setup:
We use PP-PI here. Each Product carries only one phase. Example: The Master recipe of Roasted Cashew Product will have only Roasting operation. 0010 operation & 0020 phase.
So considering the above, whether it is possible? If yes, how to meet this requirement? What setup needs to be done for it in Recipe and Resource?
Kindly advise experts as this is new for me.
Regards,
Jeffrey