Skip to Content
0
Jan 04, 2023 at 08:03 PM

Sales Order ATP and how to Leverage Capicity

46 Views

How are you guys handling cases where you get sales orders for large qty's of a material. When you configure a material you can set lead times for purchased or manufactured materials. The system assumes these at a qty of 1 for demand. How do you setup the system to handle cases where you get an abnormal order for say 100 and you can only produce 5 a day. If you have 0 in stock the system is pulling back a schedule line date = lead time for all 100 but its not possible to produce the 100 in 5 days. What am I missing here?