Hi,
I was wondering, is there a way in SAP IBP time series to start production in week 1 (respecting the min lot size) and finish it in week 2 without reconsidering the min lot size?
Example:
Line capacity: 100 pieces/week
Min lot size: 80 pieces
Demand: 140 pieces
I need the option to produce 140 pieces, of which 100 in week 1 and 40 in week 2.
Thank you for your answers,