Priorisation SAP B1

24 Views

Hi all,

we do have some issues with our supply chain. So very often our components are not on time.

So the MRP run is delaying all the production orders.

Example:

Komponent A ist on stock with 100 pcs

Finished good B demand 60 pcs deadline 31.12.2022

Finished good C demand 60 pcs deadline 31.12.2022

-> to less of C on stock to produce both, but I could produce one.

Problem:

MRP run is delaying both orders to the next delivery of item A.

How to solve this, that the system is already showing we can produce B or C without delaying demand of item B or C.

Backround: The ship date for our customer is alwayes on monday so all the orders are with same due date.

Thank you!