Hi all,
we do have some issues with our supply chain. So very often our components are not on time.
So the MRP run is delaying all the production orders.
Example:
Komponent A ist on stock with 100 pcs
Finished good B demand 60 pcs deadline 31.12.2022
Finished good C demand 60 pcs deadline 31.12.2022
-> to less of C on stock to produce both, but I could produce one.
Problem:
MRP run is delaying both orders to the next delivery of item A.
How to solve this, that the system is already showing we can produce B or C without delaying demand of item B or C.
Backround: The ship date for our customer is alwayes on monday so all the orders are with same due date.
Thank you!