MRP Planned order start date mistake

72 Views

Hi Expert,

We have a planned order, GR processing time = 10 , Planned Delivery Time = 18 , Lot Sizing Procedure = 'WB' ,

that is correct , available for Planning = 2023/02/24 , Order End Date = 2023/02/10, because GR processing time = 10,

but Planned Delivery Time = 18, why Order Start is 2022/12/27 not 2023/02/10 - 18 days?

Please help.