Hi all,

I worked a lot with standard SAP and changed to an other company working with SAP Business One.

In the other SAP it was possible to set a safety time on specific items. Do you know if there is any similar function in SAP B1.

Background:

Due to logistics reason, we need a two days buffer between the end of our production order and the delivery date of our customer orders. It’s important for us that MRP is always considering this additional time.

Same for our purchase orders. They we need one day at goods receipt so there must be a buffer of one day between the delivery date and the start date of our production order. This should be considered in the MRP run.

Does anyone have a solution for this?