Hi there, I am creating a maintenance strategy using 'time' as the scheduling indicator. For each cycle, i will put in 'Subsequent' Days to set the basic finish date for WO triggered. For example, 7 days for 1Week cycle.
However, this is not reflected in triggered WO. Regardless of cycle, the WO basic finish date is always the same as WO basic start date.
Please help and thank you.