Hi Team,
When we are creating the process order manually and changing the scheduling dates (start & end dates) by adjusting the master recipe hrs, same order dates are not reflecting in S4 PPDS / Product view (rrp3).
I understand planning & scheduling happening in PPDS, but due to special scenario we are creating process order in S4 manually.
Please suggest for any standard setting available to sync the scheduling dates. Thanks.