Skip to Content
0
Dec 08, 2022 at 09:45 AM

PO with reference to contract,

31 Views

Hi, we are trying to release PO with reference to the Contract, the system is picking material lead time and does not allow us to create a PO, as material lead time is going outside of the contract validity period, kindly let me know the setting in which I will direct the system to consider only the contract validity period rather that consider material lead time as a parameter to release PO.