Hi experts,
As per our business needs,
on 1st week of every month,
3 1/2 months demand plan will be given by marketing team...
Our planning team will give 1.1/2 months firm plan and release PR and planned order to execute in all levels.
But,Rest of 2 months forecast visibility only will be given to purchase team for their vendor to plan the Raw materials and STO for interunits ....
All the forecasting should be run in inactive version and the requirements also need be transferred to vendor and STO as per the purchase info record and Inhouse assey items .This is only the forecasting requirements to plan the activity in advance...
Is there any way ,to do this activity in SAP....
Please guide