Dear Gurus,
I have tried to run Cost Estimate CK11N/CK40N for Semi finished/Finished items, but the Raw materials price is not correct as expected.
1. Configure OKKN:
2. Costing information of a raw material
However the Cost estimate result is taking the Standard price of Raw material instead of Moving price as configured in OKKN.
Any inputs are highly appreciated.
Thank you.