CO-CK11N does not get the price setting from OKKN

111 Views

Dear Gurus,

I have tried to run Cost Estimate CK11N/CK40N for Semi finished/Finished items, but the Raw materials price is not correct as expected.

1. Configure OKKN:

pic1.png

2. Costing information of a raw material

image.png

However the Cost estimate result is taking the Standard price of Raw material instead of Moving price as configured in OKKN.

Any inputs are highly appreciated.

Thank you.