Hi Experts,
Please I have a question on the impact of Assembly scrap on Planned orders in MD04, I created a planned order with quantity = 36, my assembly scrap = 0,5%, min lot size =1 and rounding value = 10.
In MD04, I see the planned order on the correct date I created, but with a quantity = 34, and with a scrap of 2.
For me the calculation is the following :
Scrap quantity = 36 * 0,5% = 0,18 pc ---> With min lot size it becomes 1PC so I should see in MD04 a planned order = 35PC and not 34 PC
But it seems that system is using the rounding value 10, which makes the scrap quantity = 1,8 PC, and it rounds it to 2PC.
Can you please clarify for me the calculation of scrap on planned orders in MD04 ? thank you !