Hello all,
I need your help with a little issue.
I have several machin that can produce différents goods. but sometime, my machine have to produce twins references.
the point is that i have to plan the production and sometimes, i have differents needs on each one.
unfotunately, the part A need 0,5 sheets of material and the part B too
if i need to produce 100 A and 50 B, i will buy 75 sheets, but actually, i need 100 sheets to deliver goods on time.
do you have any idea for me?
thanks