Dear All,
We are using Characteristic Dependent Planning (CDP) to plan at HANA PP/DS. According to help document , the CDP scenario supports both make-to-stock (MTS) and make-to-order (MTO) planning scenarios.
After create production order at PPDS with configuration , I create new sales order. If I use a material variant to create MTS sales order, existing production order can match up requirement and heuristic won't generate new plan. Or I create a MTS sales order which has different configuration with existing production order, heuristic generate new plan. it seems like CDP function workable.
But when I use a configurable material to create production order at PPDS and MTO sales order, they never peg to each other and heuristic always create new plan even they have the same configuration. Is it correct or I miss any necessary setting?