Hi All,
I have a question on deactivating the requirement without reducing the unconsumed PIR in the MD74
I tried searching the community but couldn't find an answer for this yet.
Problem is as below
2 requirement plans maintained
Plan - ZNOV with material A, and with planned qty 1000 in the month of November
Plan - ZDEC with same material A, and with planned qty 1000 in the month of December
No customer requirement yet assigned for both the demand plans.
Now i want to deactivate the November month requirement using transaction MD74.
For the parameters i choose, plant , requirement plan No as "ZNOV" and re organization date (Key date) as 30-NOV.
Then Deactivate checkbox marked and executed
Expected behavior is to deactivate only the requirement of material A maintained in the plan ZNOV.
However i observe that for both the plans ZNOV and ZDEC requirements for material A have been de activated
Why the same material in a different plan got deactivated though i specified the plan name in the parameter?
Is re-organization period ,doesn't relevant for deactivating requirement?
Please explain the reason for this
Appreciate your inputs.
Thanks and regards,
Arjuna