Hello experts! i have a doubt regarding CK11N for a specific (and very particular) SF material.
We have a BOM with only non-valuated items. The cost of this BOM in CK11N is zero and it´s correct.
We have a Recipe with labour and energy activity types. The cost of this Recipe in CK11N is 40 USD and it´s correct.
The issue starts in CK24: The system shows planned price zero (and not 40 USD) and the price is not updated in the material (we don´t have any error in the process). So i´m wondering if this is the standard behaviour of the system: is it possible calculate the standard cost for a SF material with only activity prices?
Thanks in advance!
The prices of the non-stock item should be updated irrespective of the item category. Could you please check the activity price calculation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.