Cost center is picking from OKB9 for MBST t code

124 Views Last edit Nov 22 at 03:53 PM 2 rev

Hi,

I have posted GR with movement type 501 through MIGO and cost center i have entered manually 1000 (Cost center).

But the same material document i have cancelled through MBST t code, but cost center is picking from OKB9 (Default cost center 2000), actually cost center needs to be pick up from original material document number, but it was not picking.

And if i cancel same material document through MIGO, then it is picking correct cost center (1000) from material document

I am getting problem with MBST t code only, our business do not want to cancel through MIGO t code.

Could you please suggest me on this?