cancel
Showing results for 
Search instead for 
Did you mean: 

Splitting a position of a Freight Unit

t_jungesblut
Participant
0 Kudos

Hello experts,

I assigned one Freight unit to a Freight Order. The Freight Unit contains one position containing two products. The customer would like add two packages to the Freight Order and fill each of the two packages with one of the two products.

Is it possible to split the position of the Freight Unit to then drag&drop the individual products into the individual packages? Currently it seems like only a position as a whole (quantity=2) can be moved into a single package.

Kind regards,

Tim

Accepted Solutions (0)

Answers (5)

Answers (5)

0 Kudos

Hi Tim,

I have the same error when we try to split a Freight Unit. "Internal error;freight unit building failed"

Do you solve it?

Regards,

t_jungesblut
Participant
0 Kudos

Sorry, no. In the end we moved the packaging process to EWM

former_member809312
Contributor
0 Kudos

Hi Tim,

You can split FU manually as I mentioned or automatically in the Freight Unit Building Rule Example you have one SO with 1000 kg but you need each FU with 100kg, them you set up it in the FURB once it integrated in TM will split.

Check if all the customizing you have set up are according: Creation and Editing of Freight Units | SAP Help Portal

A possible for split in this note 2382853 - "...item type does not allow splitting" in FU from ERP Order in SAP TM - SAP ONE Support L...

Regards

Rogerio

0 Kudos

Hola Rogerio,

¿Es posible dividir una FU usando la herramienta ASR?

Estamos utilizando la aplicación 'Cargar o descargar órdenes de flecha' y lo que hacemos es:

1. Fijar en carga finalizada uno de los 2 bultos de la FO

2. Fijar 'Parar en carga finalizada'

Resultado: no divide la FU.

Gracias y saludos 🙂

0 Kudos

Hello Rogerio,

Is it possible to split a FU using the ASR tool?

We are using the 'Load or Unload Freight Orders' application and what we do is:

1. Set one of the 2 packages of the FO in finished cargo

2. Set 'Stop on finished loading'

Result: does not divide the FU.

former_member809312
Contributor
0 Kudos

Refer to link for ASR integraton

Freight Unit Split and Mass Data Changes | SAP Help Portal

Also try to open the last message "Action has not ......" and check the values there for the error which filed was validated.

former_member809312
Contributor
0 Kudos

remove the FU from the FO them split it, check if give error.

t_jungesblut
Participant
0 Kudos

Hi Rogerio,

I tried using a Freight Unit which hadn't been assigned to a freight order yet. Unfortunately it still doesn't work. I also tried to implement different building rules.

All in all the process seems very time-consuming, is this really the only way to split a freight unit?

former_member809312
Contributor
0 Kudos

Unsigned the FU from the Package 30 then Save FO. After that open FU in another Tab the click on

them here you can split it

Note the number of the new FU to plan it in the same FO them you can put each product Item to a package item in the FO.

t_jungesblut
Participant
0 Kudos

Thanks for the info. How do you proceed after the second screenshot you posted to make the split?

Would I first need to create a new Freight Unit or would a split create a new Freight Unit? Right now the few configurations I tested resulted in the following error:

I'm not sure about the settings in the screenshot, but different variations had the same error.

former_member809312
Contributor
0 Kudos

Hi Tim,

Ho do you are packing it?

If you are using Handling Unit, it will populate automatically in the FU/FO each product with a packing material, and you don't need to split the FU only in case some of that product should not be planning in same FO.

If you want to do it manually you can split the FU each one for a single material them plan it in the FO and insert it FU into a packing material in FO.

Regards
Rogerio

t_jungesblut
Participant
0 Kudos

Hi Rogerio,

thanks for the reply. I'm trying to manually split the FU. Here's a simple Freight Order as an example :

I would like to split the Freight Unit between the two packages. I'm guessing the Button "Split Freight Unit" would allow me to do that. However, that button isn't available/allowed in this case. Do I need to make adjustements in the systems and what would those be?