on 10-25-2022 7:51 AM
Hi,
Whenever I make a forecast from Nov 2022 to June 2023 and run the MRP wizard on 25 Oct 2022, It shows order recommendations in red color for most of the parent items. I think it might be due to some common components used in parent items that are being recommended in the next month i.e. Nov 2022 due to 60 days lead time of those components.
Is there any way to show which components cause delays from forecast and highlight the order recommendations of parent items as red in MRP ..?