DB02 Space Statistics - how to change interval and measurements?

In DB02, Space Statistics history, how do we change the interval and/or number of measurements? Ours seems to be lagging a week behind. We run update job once a week on Thursday night. Right now DB02 shows current data run on 5/18/06 but history stops at 5/11/06. We would like history up through 5/18/06. Is that possible?

TIA,

Margie Teppo

Perrigo Co.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 23, 2006 at 07:30 AM

    The frequency of the file statistics collection can be controlled through ST03 -> Collector and Performance DB -> Performance Monitor Collector -> Execution Times. For the table history, you need to loook at the entry for report name RSDB_TDB (in older releases: RSORATDB). If the setting is correct, you should check the job logs of the job SAP_COLLECTOR_FOR_PERFMONITOR at the time when you were expecting the collection to run. You can also submit a manual collection through DB02 -> Refresh File Statistis (Background). This will submit a job RSDB4090, and if you don't get the history data as expected, you should check its job log for potential errors. If this doesn't solve your problem, you can open a customer message for SAP, so that the SAP support can look at your system.

    Kind regards, Christian Bartels.