Hai all,

I'm using SAP S/4HANA CLOUD 2208 version. While using "Manage work center capacity" app whenever I click Edit button (top right corner) to change capacity details the system is showing an error as "Maintain an active version in change work center capacity app to continue".

Could someone help me to solve this error. thanks in advance!!

JulianoRomanato
Product and Topic Expert
Product and Topic Expert

Hello suresheswar.

How are you? I have excluded the Tag "SAP S/4HANA Cloud" and included the Tag "SAP S/4HANA Cloud for Manufacturing" for this question, as Work Center Capacity is a Topic of Manufacturing Line of Business.

Regards.

Juliano Romanato.

Accepted Solutions (1)

Accepted Solutions (1)

Prabha_A
Advisor
Advisor
0 Kudos

Hi Suresh,

Please make sure that you have maintained the Active version (01) in the Work Center as shown below,

Hope this resolves your query. Please mark the answer as replied if it resolves your query.

Thanks,

Prabha A

Suresh_Eswaran
Participant

It resolved the issue, thank you!!

Suresh_Eswaran
Participant
0 Kudos

Hi, how are you!!! Could you please confirm whether production order splitting and merging option available in S4Hana public cloud or not? If available pls advice how it can be done and the prerequisites if any!! thanks in advance!! prabhasubbulakshmi

Prabha_A
Advisor
Advisor

Hi suresheswar,

Production order split functionality is not supported as part of SAP S/4HANA Cloud 2208. But it is expected to have this functionality in future releases.

Thanks and Regards,

Prabha A