Non Stock material Cost not getting reflected in Value Category

sp0123
Participant
0 Kudos

Dear Experts

I have created an PM Work Order with Non-Stock Material.

I have followed all the steps

IW31--> IW32 (Release)---> ME21N (PO)--> MIGO

After these steps, when I opened the order under the cost tab, the non stock material is not displayed in the Non Stock material Value Category, instead the cost of the material is displayed separately. Please refer to the attachmentcost.jpg

Could you please suggest, how to display the cost under the value category- Non Stock Material? Is there any configuration, which needs to be changed

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

GL or range of GL maintained in Value category for non stock material ,need to take same GL in component tab for Non stock material .Then only in cost tab cost will appear in Non stock material value category.

Please let us know if issue still persist after applying this solution .

Answers (4)

Answers (4)

sp0123
Participant
0 Kudos

Thanks for the reply. There were some mismatch in the G/L account. After rectifying, the problem got resolved

peter_atkin
Active Contributor
0 Kudos

Check that the G/L account for the non-stock material is covered within the Cost Element Group US05_VCAT3 (image VC21).

The Cost Element Group can be viewed via KAH3.

PeteA

sp0123
Participant
0 Kudos

Thanks a lot Pete. here were some mismatch in the G/L account. After rectifying, the problem got resolved

pavan_kumarcs
Active Participant
0 Kudos

Shiv Kumar

Also maintain the following configuration.

SPRO->Plant Maintenance and Customer Service->Maintenance and Service Processing-> Functions and settings for order types-> Costing data for maintenance and service orders -> Assign costing parameters and Result Analysis Key

Regards,

Pavan

sp0123
Participant
0 Kudos

Thanks a lot 🙂

peter_atkin
Active Contributor
0 Kudos

Check your value category settings in the IMG:

SPRO->Plant Maintenance and Customer Service->Maintenance and Service Processing->Basic Settings->Settings for Display of Costs

PeteA

sp0123
Participant
0 Kudos

Hi Pete

What exactly should I look at those nodes? For your reference I am sharing the screenshots with you

vc1.jpg vc2.jpg vc21.jpg vc3.jpg vc4.jpg vc5.jpg