hi guru
in my company we use the RCCYMAB2 background job, for leveling capacity, I try to outline my problem, this is the scenario, example:
- work center set for 1000 minutes available capacity
- on this center we have already released PP production orders which consume 350 minutes (order fixed)
- the program levels planned orders for the total capacity of the center, which is 1000 minutes
the desired is to level planned orders for only 650 minutes.
we are currently forced to manually modify the total capacity of work center each time, in order to reduce it from 1000 to 650 minutes.
is it possible to configure SAP to consider production orders, when leveling planned order?
many thanks in advance