hi

iam creating new activity with out using (Copying) any SAP Standards., so in order to create follow up documents to my activity how i should update?

how follow up will determine in sap crm

regards

vinay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 23, 2006 at 04:56 AM

    Hello,

    I think the approach in this case should be to define a dummy transaction type. Map this dummy transaction type to Activity in Copy control. The the actual structure-to-structure mapping you need to achieve through BADI & finally commit it. If the follow up is an Activity, you need to map all the required exporting parameters of CRM_ORDER_MAINTAIN to your dummy transaction.

    I have not exactly done this ever, so you can help me correct my approach if I am not correct.

    Best REgards,

    Vivek