SAP PPM Capacity planning

I am looking for a BADI that gets triggered upon saving the capacity planning values within a Portfolio Item.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 04, 2017 at 08:22 AM

    Dear Ananth,

    When the value should already be changed after setting the capacity planning value and pushing "enter" - you can use an exit in

    /RPM/CL_FIN_CAP_PLANNING_API, method CAP_GROUPS_MODIFY. While saving the capacity planning datas you can use BAdI

    /RPM/EX_CAP_PLAN_BADI.

    Best regards,
    Judith

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 28, 2017 at 09:06 AM

    Dear Ananth,

    you can use BAdI /RPM/FIN_CAP_PLAN for capacity planning. (BAdI /RPM/EX_FIN_PLAN can be used for financial planning)

    Best regards,

    Judith

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Judith,

      Sorry for the delay in response. I just got the opportunity to check this. We tried to put a break point in the method modify_cap_plan, but the BADI does not get triggered. Our intention is to capture the capacity planning amounts that have been entered. Kindly let me know.

      thanks