on 09-23-2022 5:59 PM
03 - inprocess inspection produces one inspection lot at order create. I have 2 scenarios
1)I want to create multiple in-process inspection lots for process order. How to set this up?
2)I want to create in-process inspection lot fo process order , but UD accept, should post the component back to process order for consumption , UD-reject should put the sample size component scrap
You have Adhock inspection type ( I think 89) where you can decide Toto post to stock ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear rajendrasapz,
thank you for the details provided.
The lot origin 03 is not stock-relevant, which means you cannot post stock with such lots during usage decision.
See SAP Help
"...
Processing materials as non-stock-relevant goods
...
- 03 Production
...
Posting stock-relevant materials to inspection stock
...
- 04 Goods receipt from production
..."
As you can see the lot origin 04 is stock-relevant, which can be generated with the goods receipt (GR) to the process order.
However, there is a lot type called "early 04", which is triggered during the process order release. With the GR this early lot is then converted to a regular 04 lot.
See SAP Help:
'Early Inspection for a Goods Receipt'
Material master for the early lot:
Also, I recommend to review the inspection points option instead of the multiple inspection lots for same order. It might be an easier approach to reach your goal.
See SAP Help:
Have a nice day,
Albert
***
Read and follow the 'SAP Community Rules of Engagement' athttps://www.sap.com/community/about/rules-of-engagement.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.