on 09-23-2022 6:03 PM
I am creating process order.
I have maintained all the operation time in recipe
Also production version is there.
But still there is no operation time.
Kindly provide your support.
Hi Raghavan,
Hope you are doing good!!
The data you have provided is not sufficient to revert back with the exact answer.
Please make sure that you have created the Master Recipe as per the scope item 3X9 (Create Master Recipe-MDS). Kindly use the below link to download the Master Data Script (MDS) for Master Recipe (3X9)
Please mark the reply as answered if you find this useful.
Thanks,
Prabha A
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I missed to maintain the Activity types and formulas in work center, Since the Values are not calculated in process order.
Also there are no formulas for machine, labor, formulas in scheduling and capacity tab of processing unit work center category.
Inside operation I was not able to see the activity hours. Now I can able to see.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.