Hi All,

When we apply fixing indicator for product chart but fixing indicator (red line) is not showing in the resource chart.

We configured new Object id for colour change for planned order (yellow color - planned order & Blue for process Order in resource chart) and added 2 new no. (1 for planned order in Yellow colour & 2nd for Fixing ), as shown below -

Please let us know if we missed something for fixing indicator in resource chart. Thanks.

Also added in the decision table -