Estimate the count of Test cases based on Fits/Gaps workshop,

piyushmalhotra
Explorer
0 Kudos

Do we have a model/calculator to estimate the number of expected test cases from FIT's/GAP's identified during the Fit Gap Analysis phase?

I am having S4 HANA Greenfield implementation, wherein we just completed Fit to Standard workshops in Agile. Wherein we have collate the data like this : - Fit are identified as Standards what SAP says, Any deviation which require little config change from Standard as consider as DELTA whereas Gaps are the one which require from scratch (new Development). Please guide.

piyushmalhotra
Explorer
0 Kudos

@kstledger

0 Kudos

Fit Gap items is not the right source for Test Cases of UAT.

It can be right source for Developments and UT/SIT Test cases.

But when you want to finalize UAT test cases, few factors to consider -

1. BPMN - business process - which are in scope processes ?

Use SMC criteria and Critical will be part of UAT

2. FIT - what are priority and cirtical requirements and link into BPMN.

This will be additional scope.

All other standard processes will be only part of training

3. GAPs -

Link into BPMN process steps.

Legal gaps - mandatory in scope

Other country Critical gaps - to be added.

Other country gaps - based on Efforts required for testing - to be accomodated. - should be part of UT/SIT and test review can also suffice.

hope this helps.

piyushmalhotra
Explorer
0 Kudos

Can we take

Delta - 20 % of Numbers of user stories

Gaps - 40% Of the number of user stories

Accepted Solutions (0)

Answers (3)

Answers (3)

CKGurav
Advisor
Advisor

Hello Piyush,

Every implementation project is unique and needs some project-specific strategy when it comes to defining the test cases. You can review the Test Strategy Task from SAP Activate Roadmap for S4Hana Cloud Implementation for a guidance.

However, as you already have identified the FITs for your implementation project, then it would be wise to consider leveraging standard Test Scripts, which are available on the SAP Business Process Explorer, SAP has provided test scripts for all the standard Scope Items, You can review these test scripts and estimate how many of these scripts can be reused and determine the scope for new test scripts that might be needed. You can follow the instructions provided in the Task "Define a Test Case" in the SAP Activate Roadmap for S4Hana Cloud Implementation.

piyushmalhotra
Explorer
0 Kudos

Thank You for answer, please guide me if we need to convey some approx. numbers to the customer for their UAT execution at resources front.

CKGurav
Advisor
Advisor
0 Kudos

Hello Piyush,

In general, UAT (or BAT- Business Acceptance Testing) are the tests performed by the key users/business users from the customer implementation team. Regarding resourcing, it would be subject to the scope and how the users will be engaged in executing the business process.

In my personal experience, We usually don't provide resource estimation for UAT as its owned by the customer team; however, this can be discussed with all the key stakeholders while defining your test strategy.

Eugevi01
Explorer

Hi. for UAT you need to know the "processes". In other words, ok, if you did the fit-gap workshops, first you have presented the processes included in the scope. Each GAP is also part or solve any out of standard process.

So, you need to take the processes with all their steps and based on that process you will be able to estimate the test scenarios. For example: "national purchase of materials from our production", ”national purchases of material with third party parts”, “purchase of local services”, “asset acquisitions without Purchase Order”, “asset acquisition with PO”, etc.

Remember for UAT you need to think on “end-to-end” process.

piyushmalhotra
Explorer
0 Kudos

Thank You for kind and detailed response but suggest if we can derive with some estimates for UAT Test case count ....since based on the same customer would forecast the resource required.

Eugevi01
Explorer
0 Kudos

Hi , "but suggest", Sorry, what i said it is what i can suggest. Again, Based on the scenarios and the steps involved on them the customer needs to estimate the resources. In my experience there is no a mathematical formula, Because the customer is the one that knows their resources, who knows how many people are available for that kind of assignation, and if the resource can be assigned FT o PT. Regards

hitechrobot
Explorer

Only with numbers of GAPS and DELTA identified , I dont think we can find out expected test cases , you have to categorize further in various task and subtasks . Refer to SAP Roadmap for S4HANA Greenfield implementation ,it provides accelerator for Test Strategy .

piyushmalhotra
Explorer
0 Kudos

The intent is to convey business forecast the resource number required for UAT cases to business ?