We have a requirement to plan the material in forecast for Production BOM (usage1) and Sales BOM (usage 5) as well, sales BOM will have multiple levels & need to explode Sales BOM during MRP run to get the supplying elements with net requirement at all the levels and the materials will be used for kit assembly when they recieve the sales order.
We attempted to explode the Sales BOM by making a few adjustments in SPRO. Configured the Z selection ID, added Priority Indicator 3 with BOM usage 5, and assigned the selection ID to the appropriate Plant, but the expected result was not achieved, we can see planned order for only header material, but the structure is not being exploded in MRP. we can see the entire structure explosion in CS11 or CS12 with BOM application SD01 but not at the time of MRP run.
Even after activating Application (Shown in screenshot) to consider MRP and Planned order, failing to explode the BOM.
If anyone has come across this situation, please suggest if there is anything we are missing. Thanks in advance.